CA Inter doubt

AS7 ... Computation please when contract value is 370

Image attached to the doubt: AS7 ... Computation please when contract value is 370

Asked by Mani28 Mar 2025663 views

5 answers

  1. Meet · 30 Mar 2025

    So that I this Question certified cost ignore

  2. Meet · 30 Mar 2025

    If Cost Til date not given in que .. then work certified and work not certified added

  3. Meet · 30 Mar 2025

    Because cost Til date and further cost directly given in the Question

  4. Mani · 30 Mar 2025

    Why haven't you considered the certificated cost in actual cost?

  5. Meet · 30 Mar 2025

    Cost Til date 360 Lakh + Further cost 50 Lakh ____________________ Total cost 410 Lakh % completion = Cost Til date __________*100 Total cost i.e 360 Lakh _______*100 410 Lakh =87.80%. approx=87% Revenue reconisd 370*87% = 321.9 approx Answer 320 (A)