A contracts with B for a fixed price to construct a house for B within a stipulated time. B would supply the necessary material to be used in the construction. C guarantees A's performance of the contract. B does not supply the material as per the agreement. Is C discharged from his liabilities? The answer to this question is given in the module 'discharge of principal debtor' but this is the topic of 'creditor fails to perform his duty'?